A project charter is the short document that authorises a project to start. It states why the project exists, what it has to achieve, what is in and out of scope, the main milestones and budget, who sponsors it, who runs it and what that person may decide on their own. The sponsor signs it, and from then on it is what every argument about the project gets checked against.
PMI's PMBOK Guide defines it in roughly those terms: the document that formally authorises a project and gives the project manager the authority to use the organisation's resources on it. In practice, most charters are written for a more ordinary reason. Somebody senior needs to agree to the goal and the boundary in writing before the team spends a month on it, and the charter is where they agree.
What to include in a project charter
These are the sections in the order a reader needs them. A small project merges some and drops others; the block further down shows which.
- Purpose. The problem and why it is worth solving now, in two or three sentences.
- Objectives. Measurable outcomes with a number and a date, so the closure report can check them.
- Deliverables. The things you will hand over, each a noun with a format.
- Scope. In scope and out of scope, as specific as each other.
- Milestones. Four to six dates that mean something, not the full schedule.
- Budget. Money and people's time, and who can approve more.
- Roles. Sponsor, project manager and the leads of each workstream, by name.
- Stakeholders. Who is affected and how they hear about progress.
- Risks and assumptions. Three to five of each.
- Authority. What the project manager can decide without asking.
- Approval. Names, roles, dates.
Project charter template
Here is a complete charter for a mid-sized internal project: a software company moving its customer support from a shared inbox to a helpdesk tool. Copy it and replace the facts with yours. Every line is there because a real project needed it.
PROJECT CHARTER: HELPDESK MOVE
Version 1.0, 8 December 2026
PURPOSE
Support requests arrive in a shared inbox with no owner and no history.
Median first reply is 2 working days and customers ask the same thing
twice. This project moves support to a helpdesk tool before the spring
peak, when volume roughly doubles.
OBJECTIVES
1. Median first reply under 8 working hours by 30 April 2027.
2. Every request has a named owner within 1 hour of arriving.
3. The shared inbox closed for incoming mail by 31 March 2027.
DELIVERABLES
- The helpdesk tool, configured for 12 agents
- Routing rules for the 5 request types in Appendix A
- 40 saved replies, reviewed by the support leads
- A 2 hour training session, recorded, plus a 4 page agent guide
SCOPE
In scope: email and the web contact form; tickets from the last 90 days
imported; reporting on first reply time and backlog.
Out of scope: phone support; live chat; importing tickets older than
90 days; changes to the website beyond the form's address.
MILESTONES
15 Jan Tool chosen and contract signed
20 Feb Configuration and routing complete
10 Mar Agents trained
31 Mar Shared inbox closed to incoming mail
30 Apr Objective 1 measured and reported
BUDGET
Licences for 12 agents for 12 months (quote in Appendix B).
20 days of the operations team, 5 days of IT.
Overruns above 10 percent go back to the sponsor for approval.
ROLES
Sponsor: Dana Ruiz, Head of Customer Support
Project manager: Sam Okafor
Configuration: Lee Park
Training: Priya Nair
IT contact: Marco Bianchi
STAKEHOLDERS
Support agents: weekly 15 minute stand up from 12 January
Sales: a note at each milestone
Finance: licence approval only
RISKS
- Agents keep answering from the old inbox. Mitigation: forwarding
plus a read-only inbox from 31 March.
- The import of 90 days of tickets fails or duplicates. Mitigation: a
test import by 1 February.
- Volume rises before training ends. Mitigation: training moves to
week of 2 March if the forecast changes.
ASSUMPTIONS
- IT can set up mail forwarding by 1 February.
- No new support hires before April.
AUTHORITY
The project manager can move a milestone by up to one week, change
configuration and saved replies, and approve spend inside the budget.
Changes to scope, objectives or budget go to the sponsor.
APPROVAL
Approved by Dana Ruiz, Head of Customer Support, on [date].
The template is about two pages when laid out, which is right for a project of a few months touching three teams. The same structure works for a client project. There, the price and payment terms stay in the statement of work and the charter refers to it.
Build yours
Pick the size of your project and who backs it. The sections and their order change, with an example line from the same helpdesk project under each, and the outline copies as text.
Build the charter for your project
Pick the size of the project and who backs it. The sections change, with an example line under each.
10 sections. Two to three pages.
Draft it from the request that started the project, then send it to the sponsor alone for comments before anyone else sees it.
1. Purpose
Two or three sentences: the problem, and why it is worth solving now.
Support requests arrive in a shared inbox with no owner and no history. Replies take two days on average and customers ask the same thing twice. This project moves support to a helpdesk tool before the spring peak.
2. Objectives
Each one measurable, with a number and a date, so the closure report can check it.
Median first reply under 8 working hours by 30 April. Every request has an owner within one hour of arriving.
3. Deliverables
Nouns you could hand over, each with a format.
The configured helpdesk, 40 saved replies, a routing rule set, a two hour training session, recorded.
4. Scope
In scope and out of scope, equally specific. Out of scope is where the arguments are.
In: email and the web form. Out: phone support, live chat, migrating tickets older than 90 days.
5. Milestones
Four to six dates that mean something, not a full plan.
Tool chosen 15 January. Configured 20 February. Team trained 10 March. Inbox closed 31 March.
6. Budget
The money and the people time, and who can approve more.
Licences for 12 agents for a year, plus 20 days of the operations team. Overruns above 10 percent go back to the sponsor.
7. Roles
Sponsor, project manager and the people doing the work, by name.
Sponsor: Dana Ruiz, Head of Customer Support. Project manager: Sam Okafor. Configuration: Lee Park. Training: Priya Nair.
8. Stakeholders
Who is affected and how they hear about progress.
Support agents (weekly stand up), Sales (a note at each milestone), Finance (licence approval only).
9. Risks and assumptions
Three to five of each. An assumption is a risk you have decided to accept.
Risk: agents keep answering from the old inbox. Assumption: IT can set up mail forwarding by 1 February.
10. Approval
Names, roles and dates. Approval is what makes it a charter.
Approved by Dana Ruiz, Head of Customer Support, [date].
How long should a project charter be?
Long enough to settle the boundary and the authority, and no longer. As a rough guide:
- One page for a project of a few weeks inside one team. Purpose, objectives, scope, a few dates, who is doing it, risks and a one line approval.
- Two to three pages for a project of a few months across several teams, like the example above.
- Three to five pages for a large project that needs a budget approved, with detail such as the cost breakdown in appendices.
A charter that keeps growing is usually absorbing the project plan: task lists, week by week schedules, resourcing tables. Those change every week, and the charter should not. Move them out and link to them.
Project charter vs project plan, scope statement and SOW
| Document | What it does | Who approves | How often it changes |
|---|---|---|---|
| Project charter | Authorises the project: goal, boundary, sponsor, authority | The sponsor | Rarely; a change is a new version |
| Project plan | Says how the work gets done: tasks, schedule, resources | The project manager, with the team | Every week |
| Scope statement | Defines the scope in detail, often with a breakdown of deliverables | The sponsor or the client | Through change control |
| Statement of work | Defines the work for a client, with price and acceptance | Both parties, as part of a contract | Through change control |
On a small project, the charter's scope section is the scope statement. On client work, the statement of work often comes first, and the charter is the internal document that turns it into a project with names and decision rights.
Who writes it, and who signs it
The project manager usually drafts it, because they will have to live inside it. The sponsor approves it, because they own the budget and the outcome. In some organisations the sponsor writes it and hands it to the project manager, which works if the project manager gets to push back before it is signed.
A sensible order:
- Draft it alone from the request that started the project.
- Send it to the sponsor first, alone, for comments. You want their objections before anyone else's.
- Share it with the workstream leads, and give them a date for comments.
- Hold the kickoff meeting, where the purpose and the out of scope list get said out loud in front of everyone who will do the work.
- Get the approval in writing, with a date.
If people disagree about what the project is for, reverse the first two steps. Get the sponsor and the people who disagree into one meeting, settle the purpose and the out of scope list there, then write the charter from the notes. A charter drafted alone in that situation turns into a document people argue with by email.
Writing each section well
Purpose
State the problem in terms of what it costs today. "Customers wait two days for a reply" is a purpose. "Implement a best in class helpdesk" is a solution wearing a purpose's clothes, and gives nobody a way to tell later whether it worked.
Objectives
Each objective needs a measure, a target and a date. If you cannot measure it, you cannot close the project against it, and the closure report becomes a matter of opinion. Three objectives are plenty; ten means nobody knows which ones matter.
Scope
Write the out of scope list with the same care as the in scope list. Most of the requests that arrive in month two are for things nobody excluded in writing. In the example, phone support and old tickets are both things somebody would otherwise have assumed were included.
Milestones
Pick the dates that mean something to the sponsor: a decision made, a thing live, a thing switched off. The detailed schedule belongs in the plan, where a timeline or a Gantt chart can carry it.
Risks and assumptions
An assumption is a risk you have decided to accept. Writing it down means that if it turns out false, everyone already agreed it was the cause. "IT can set up forwarding by 1 February" is an assumption that saves an argument in February.
Authority
This is the section most charters skip, and the one that saves the most time. If the project manager can move a milestone by a week without asking, say so. Every decision that has to go up to the sponsor costs days.
Common project charter mistakes
- No measurable objective. The project cannot be closed, only abandoned.
- An approval nobody gave. A charter without a name and a date on the approval line is a draft.
- A charter that is really a plan. Tasks and week numbers belong elsewhere.
- Scope with no exclusions. Every gap becomes a request later.
- Written once and never opened again. The charter is what the weekly status report measures progress against. If its objectives and dates are not visible there, the team will drift from them.
Keeping the charter where people will find it
A charter is useful for as long as people can find the current version. A file attached to an email in December is out of date by January and nobody knows which copy is right.
In Quixli, the charter can be one document the sponsor and the leads work on together. Share it by email with Can comment and the sponsor leaves comments on the exact sentence they want changed. Quixli also keeps earlier versions as you edit, so after approval you can see what the charter said on the day it was signed. For a project that spans several teams, the project overview page shows how a single document can carry every stream and its dates once the charter has been approved and the work begins.